Construction Timeline

July 29, 2021 - September 21, 2021

Staging yard/ screening plant set up

Work
August 23, 2021 - October 4, 2021

Silt Fence

Work
September 09, 21 - September 25, 2023

Traffic Control

Work
September 09, 21 - October 14, 2021

63″ HDPE pipe install

Work
October 14, 2021 - October 28, 2021

Install VPI Bends & Air vent

Work
October 18, 2021 - April 1, 2022

Install concrete outflow structure & fencing

Work
October 28, 2021 - July 08, 2022

63″ HDPE pipe install

Work
June 09, 2022 - September 02, 2022

Grading slope of Causeway

Work
July 08, 2022 - July 29, 2022

Install blow off/Manhole/Air vent

Work
July 08, 2022 - September 02, 2022

Install pipe encasement around blow off/Air Vent

Work
July 29, 2021 - February 10, 2023

63″ HDPE pipe install

Work
February 10, 2023 - March 03, 2023

Install open cut casting crossing Antelope Dr.

Work
March 03, 2023 - March 24, 2023

63″ HDPE pipe install

Work
March 24, 2023 - April 07, 2023

Install VPI bends and air vent

Work
April 07, 2023 - April 28, 2023

Pour Pipe encasement for air vent

Work
April 07, 2023 -May 26, 2023

63″ HDPE pipe install

Work
May 26 , 2023 - July 31, 2023

Install Rip Rap & outlet channel

Work
May 26, 2023 - June 30 , 2023

Pressure testing of the 63″ HDPE pipe

Work
May 19, 2023 - August 14, 2023

Grading slope on Causeway

Work
August 14, 2023 - September 25, 2023

Clean up

Work